Define RRP Resource Routings

Explanation

This activity is used to enter or modify the resource requirements for a master-scheduled part or a product family part. This information is used when you run RRP. Usually, a resource is machine capacity, and its resource requirement is machine hours. A resource also can be storage space, personnel, and transport capacity. You can link a resource requirement to a specific operation.

Prerequisites

This activity requires that work centers to be used by RRP must have been registered.

System Effects

As a result of this activity, there are no system effects.