Explanation

Use this activity to maintain the period calendar to be used in the system. A record must be created for each period in a year for which planning is done. You can define the forward planning by different period units, which means that you can have daily, weekly, monthly, or quarterly periods defined for the same year. For example, to create weekly periods for a calendar year, you would create 52 records, with each record being appropriately numbered and its length defined by seven-day begin and end dates.

 

Prerequisites

There are no prerequisites for this activity.

System Effects

As a result of this activity, the system creates a period unit calendar for use within the system.