View Master Schedule Level 0 Part

Explanation

Use this page to study the Level 0 parts that have long-term forecasts. Level 0 parts are not actual physical parts, but a collective concept, a product family. Forecasts are generated for the product family, Level 0, and must be transferred to Level 1, which is the actual part level . The master schedule is created on the manufacturing level and resource demand is planned based on these parts. You can also study the part family structure, which is more commonly referred to as a planning bill, or plan structure.

Prerequisites

This activity requires that Master Schedule Level 0 parts must exist.

System Effects

No system effects.