Transfer Interim Demand Structure to DOP
Explanation
Use this activity when you want to create a DOP order structure manually
from an interim demand for a configured part. This activity requires that the
interim order was created manually. The structure of the new DOP will match
that of the interim order. You can also create a DOP from an interim demand
in customer order.
Prerequisites
- IFS/MFG Standards structures should be defined for the part.
- IFS/Configuration Characteristics and IFS/Configuration Back Office
must have been installed, and associated configurations and back office
configuration rules defined.
- To create the DOP, the part configuration revision must be in the
Released state and the structure must be in the Buildable state.
- To create the DOP structure, the interim demand header must be at least
in the Evaluated state.
- The interim demand must not be connected to any sales quotation, customer
order, or DOP order.
System Effects
As a result of this activity, a new DOP header is created in Unreleased
status, with DOP orders that match the interim demand structure.