Explanation
This activity is used to create a top DOP order. No lower level DOP structure
will be created.
To create a top DOP order click Create Structure, then
Create Top Order.
Prerequisites
The status of the DOP header should be Created.
System Effects
As a result of this activity:
- A top DOP order will be created. If serial
numbers are reserved for the DOP header, these are moved to the top DOP
order.
- The status of the DOP order will be Unreleased unless
the orders are automatically released. In that case, the status will be
Released.
- If the DOP header is project specific the top DOP order created will
be tagged with project ID and activity sequence.
- A valid routing revision and buildable routing alternate will
be added for the top DOP order. If no buildable or plannable routing alternate
exist for the part a DOP log is created. If the routing is serial
effective
and no serial numbers are reserved for the DOP order a DOP log is created.
- The due date and the start date are calculated for the top DOP order,
depending on due date of the whole DOP structure, lead-time and lead-time
offset, where the lead-time is depending on lot size and routing revision
and alternate.