Net DOP Order

Explanation

Use this activity to manually initiate the automatic netting processes for a specific DOP order. You can also automatically initiate this netting process upon release of the individual DOP order. This requires certain basic data settings for DOP. For more information refer to the activity: Set DOP Netting Method.

To perform netting processes for the selected order and all its lower orders from the DOP Order page, click Net, then click Order. This can also be done from the DOP Header page after expanding the tree structure in order to display the DOP order.

It is also possible to perform re-netting when either the quantity or the structure is changed after the release; you can re-net after canceling netting relations.

Netting is performed in the following sequence:

For DOP order where the DOP header is connected to a project, the Create Pegged and Std Planned Item settings impact whether netting is allowed only from the project inventory or only from the standard inventory:

For DOP order that is netted from project inventory, netting is performed in the following sequence:

Prerequisites

This activity requires that:

System Effects

As a result of this activity: