Replan Maintenance Order

Explanation

This activity is used to replan the earliest start and/or latest finish dates of the maintenance order. If an entire maintenance visit is decided to be performed at an earlier or a later date than initially planned, the maintenance order can be moved to the new required dates and, at the same time, the planned execution logic structure (ELS) connected to it will be moved without having to regenerate the ELS.

To perform this activity, Select the Replan Maintenance Order option from Execution Logic Structure Gnatt page. In the Replan Maintenance Order dialog enter the date and time the maintenance visit is required to start and finish. If you want to reset the entire ELS back to how it was default generated, but based on the changed dates in the Earliest Start and Latest Finish fields in this dialog, enable the Reset the Execution Logic option.

Prerequisites

To perform this activity, a maintenance order in the Under Preparation status must exist.

System Effects