Enter Parts on Supplier Schedule Agreement
Explanation
Use this activity to enter the parts this agreement is valid for, or study
parts connected to a supplier schedule agreement.
Depending on the circumstances, you can handle this in two ways:
- If the tolerances and policies are identical for all parts included
in the agreement, the parts are more easily entered in the
Parts tab since these are set as default
from the agreement header unless specifically entered.
- If the tolerances and policies are specific for each customer part,
it is advisable to continue to enter the parts in the page
Supplier Schedule
Agreement Part.
Prerequisites
- A supplier schedule agreement header must be entered.
- The parts to be connected should be entered in the purchase part record.
- The sites that you need must be entered and connected to your user account.
System Effects
As result of this entry, parts are connected to the supplier schedule agreement.