About Navigation Model

A project deliverable is first created as an assembly structure. Items in an assembly structure are usually shown in the order, as they are physically connected to each other. The assembly structure is important and the main structure for project deliverables. The assembly structure enables calculations of required quantities, required dates and planned costs. Material can be reserved to parent items, by using the project deliverables assembly structure. The assembly structure is also the structure for which the material plan is created and additional plans, such as estimate, work and shipment. The assembly structure is created when entering components in Project Deliverables Design/Components. The project deliverables assembly structure is also created when copied from PDM, copied from product structure and when copied from an item configuration.

The assembly structure is important, but sometimes there is a need to show items in other types of structures. These additional structures can be defined by using navigation models. Navigational models create an alternative way of explaining a project deliverable structure. Navigational models consist of attribute values and could have names like facility, part of facility, building, room, area, segment, ship, and sections etc. These navigation models together with its attribute values are manually created. What attributes values to create, differs between industry standards, company procedures, engineering disciplines and the purpose of the model. In a navigation model, project deliverable items are grouped together by using attribute values. For example, group project deliverable items together, by using attributes values such as: facility, part of facility, building, floor level, room, area, segment, ship, sections, to create a location structure.

A detailed example can be like this: In ship building industry, ship hull is created by welding pre-fabricated sections together. Entire multi-deck segments of the hull or superstructure will be built elsewhere in the yard, transported to the building dock or slipway, then lifted into place. This is known as "block construction". The most modern shipyards pre-install equipment, pipes, electrical cables, and any other components within each section, to minimize the effort needed to assemble or install components deep within the hull, once it is welded together. At this stage, section act as a temporary location. A navigation model with attribute values for sections can be created. Steel, equipment, pipes, electrical cables and any other components can now be connected to sections.

Once the Hull is set up, actual locations like top deck, fore deck, main deck, control room, engine room start to exist. Equipment, pipes, electrical cables and any other component can now be connected to new attribute values like engine room, emergency generator and control room in a new navigation model. This structure is now used for the commissioning, operation and maintenance. The structure of the navigation model and connected components can now be copied to Asset Design and Maintenance (Equipment).

The temporary model for the pre-fabrication of sections and the model for the operation and maintenance can coexist. There is no limit in how many navigation models a project deliverable structure can be connected to.

Navigation model - Created in three steps:

  1. Create attribute values, such as facility, part of facility, building, floor level etc.
  2. Create navigation model and add attribute values.
  3. Connect deliverable items to attribute values.

Navigation model - Examples

Temporary location structure to show the prefabrication of sections during the construction phase
Attribute values Deliverable items and components are connected to attribute values
Section 1 Pre-installed equipment, pipes, electrical cables, and any other components in section 1.
Section 2 Pre-installed equipment, pipes, electrical cables, and any other components in section 2.
Section 3 Pre-installed equipment, pipes, electrical cables, and any other components in section 3.
Final location structure for the operation and maintenance phase
Attribute values Deliverable items and components are connected to attribute values
Engine room Equipment, pipes, electrical cables, and any other components in the engine room.
Main deck Equipment, pipes, electrical cables, and any other components on the main deck
Control room Equipment, pipes, electrical cables, and any other components in the control room. 

Navigation model - Templates

Navigation Model templates provide an easy way to create navigation models. A navigation model can also be saved as a template.

Navigation model - Copy to Asset Design and Equipment

A complete navigation model with attribute values, deliverable items and components can be copied to Asset Design and Equipment. A navigation model can be copied as a function structure to Equipment. A navigation model can be copied as a function, location, process, pipe system, from/to and electrical structure to Asset Design. These structures can then be transferred two-ways between Asset Design and Equipment.