Create Work Order
Explanation
Use this activity to create a work order.
Prerequisites
A work package should have been created and released.
System Effects
The work order will be created and added the following information:
- Work task plans connected to the work package are created as work tasks.
Values for Maintenance Organization and Duration
are transferred from work task plan to work task.
- Resources on the work task plan are created as resources on work tasks.
Values for Resource Group and Planned Quantity
are transferred from work task plan's resources to work task resources.
- Materials on work task plan are created as materials on the work order.