Create Work Task Plan
Explanation
Use this activity to create work task plans in order to complete installation,
test and commissioning.
Prerequisites
For a work task to be created, the following should have been done:
- Project deliverable should have been defined with a project activity.
- Gross requirements should have been calculated to get the correct quantities
and dates.
The following enables work tasks to be copied from a work task template:
- A work task template must have been created in Service and Maintenance.
- A work task template connection must have been created in Project
Deliverables and connected to a Technical Class or Asset Design
Class depending on the COPY_TO_MAINTANANCE property
value.
- If object property COPY_TO_MAINTANANCE is set to
NO, a value for class must have been entered on project
deliverable item.
- If object property COPY_TO_MAINTANANCE is set to
YES, a value for technical class must have been
attached to a project deliverable item.
System Effects
Part information on project deliverable item and where a corresponding inventory
part exist, is automatically added as material on work task plan.