Manage Materials on Work Task Plan

Explanation

Use this activity to manage materials on a work task plan. Material on a work task can be added in three different ways:

  1. Copied from a work list in a work task template.
  2. Copied from project deliverable item, when work task is created. This happens if the part defined on project deliverable item, also exist as an inventory part.
  3. Manually add materials.

Prerequisites

Gross requirement calculation should have been run.

A work task plan should have been created.

The same material can be added on several work task plans and shipment plans as longs as the total required quantity isn't exceeded. The total required quantity is calculated when gross requirement calculation is run. The quantity for the same material can be balanced between shipment plans and work task plans, so that it doesn't exceed the total required quantity:

System Effects

Material is added on the work task plan.