Explanation

Assigning budget/forecast estimate to complete values is a process where you start with a budget on one particular level and assign it to another level or move it between the branches of a structure. This helps to make sure that control and comparison is made at the correct level, where the actual values appear. Using the Assign ETC function ensures that changes made are done in a controlled manner and with the possibility of adding notes to every move.

If multicurrency budgeting and forecasting and/or project currency is used it is possible to change the currency code between the source and the destination lines. In this case the changes needs to be validated against either the Base B&F Currency or the Project Currency.
 