Analyze History Logging Data

Explanation

The history logging data consists of snapshots of activity and object connection information for all activities, including important parameters which describe the progress of your project. You can analyze the history logging data to assure that the progress performance is in accordance with your project plans, or at early stage discover any variances from the plan. History data is created either through history logging or when a baseline is created. History logging data is presented in several different perspectives:

Prerequisites

At least one history logging must have been performed. This history record can be taken either when doing a manual history logging, a scheduled history logging, or when setting a baseline revision. 

System Effects

None.