Define Consumption Point on Company

Explanation

This activity is used to define the consumption point on a company. The consumption point is the point at which the cost of the project is considered to be consumed out of the budget.

Prerequisites

N/A

System Effects

Depending on the consumption point defined, the budget will be consumed from that point onwards for all forecasts belonging to the selected company. A consumption point effects the remaining budget in the following ways:

Consumption Point Remaining Budget Calculation
Create Pur Req Line EAC - (Used Cost + Committed Cost + Cost of all PO’s not released + Cost of PRs Released + Cost of  PR’s not released)
Release Pur Req Line EAC – (Used Cost + Committed Cost + Cost of all POs not released + Cost of PRs released)
Create Pur Ord Line EAC – (Used Cost + Committed Cost + Cost of all PO’s not released)
Release Pur Ord Line EAC – (Used Cost + Committed Cost)