Enable/Disable Budget Control on Project
Explanation
When creating a new project it will be possible to identify whether budget
control rules should be enforced or not. This activity is used to enable/disable
budget control rules during the project execution.
Prerequisites
- A project should exist.
- A consumption point must be defined for the company in Project
Budget Control for the rules to be enforced.
System Effects
- Budget Control is enabled/disabled on the project.
- All project transactions created against this project will be validated
against the Budget Control rules of this project from the Consumption
Point onwards.
- If there is no budget defined for the project, you cannot create or
save transactions from the consumption point onwards.