Enable Schedule of Work Types

Explanation

This activity is used to enable Budget/Forecast Types which can be used as SOW Type to create a Schedule of Work.

Prerequisites

Budget/Forecast Types must be entered in the Forecast Type page in the IFS/Project Management.

System Effects

Enabled Forecast Types which will be made available through a List of Values for creation of new Schedule of Estimate or connect as a Production in Schedule of Work Defaults. Once SOW Type is connected as a Production it can be used to create a Schedule of Work Production.