Replan Activity
Explanation
When an activity is in Released status, it can be returned to Planned
status by selecting Replan through the Status command button.
This enables planning for the activity to be done again.
Prerequisites
- The activity must be in Released status.
- No cost, revenue or hours can have been registered on the activity.
System Effects
- The activity is in Planned status.
- Cost, revenue or hours cannot be registered
on the activity.
- The actual start date is removed.
- The activity can be cancelled or released from this status.