Explanation

Perform this activity to create a baseline for the project. A baseline is a plan against which project execution is compared and differences are measured for the purpose of project performance analysis and control. It is possible to create any number of baselines per project, whenever it is necessary due to approved changes in scope, schedule or cost. When setting a new baseline, the Earned Value Method is selected, this will determine if the Earned Value and Scheduled Work project indicators should be calculated based on baseline values or planned values. Set Baseline action command is available on Project Definition, Projects, Project Scope and Schedule and Project Monitoring pages.

Prerequisites

System Effects

Each time when a baseline has been set: