When a pegged shipment order is created against the
work task service material line, the service planner will need the
visibility of when the material will be delivered.
By using this function, you can confirm the delivery
date as below, which then will be reflected in the work task service
material line Confirmed Receipt Date column.
The date reflected in the work task service material
line Confirmed Receipt Date column will be based on below equation.
Promised Receipt date = Promised Delivery Date +
Transport Lead Time + Internal Transport Lead Time (If calculated date isn’t
a working day, the next working date will be fetched).