Handle Material

Explanation

This activity is used to receive and issue materials which is required when executing the work assignment. It initially involves to receive the required materials into an accessible warehouse by executing the respective transportation tasks. The main purpose of this activity is to Issue the required parts on the respective work task assignments.

Following procedure can be used to execute the material transportation tasks and issue the respective parts from the Subcontract Work Orders > Execute Work Lobby Page.

Using Material Summary page,

  1. Go to Lobby section for Material Summary and find material summary lines that has In Transit option.
  2. Select them and click on Receive Material command.
  3. Notice the reception of respective parts into warehouse Material Stocks.
  4. Select the same set of lines as above and observe that the Issue button is enabled.
  5. Click on the Issue command and then, Issue Material dialog opens.
  6. Pick the Location, quantity to be issued and Click OK.

Using Work Task Details page,

  1. Go to Lobby section for Ongoing Assignments and select one or few Work Started assignments.
  2. Click Work Task Details button to navigate into respective work tasks.
  3. Open the sub group for Materials.
  4. Find one or few material summary lines that has In Transit option.
  5. Select them and click on Receive Material command
  6. Notice the reception of respective parts into warehouse Material Stocks.
  7. Select the same set of lines as above and observe that the Issue button is enabled.
  8. Click on the Issue command and then, Issue Material dialog opens.
  9. Pick the Location, quantity to be issued and Click OK.

Prerequisites