Operation Block

Operation block is a tool that supports the planning, scheduling, and reporting of operations suitable to execute together on a work center, typically sharing a common characteristic value.

If the work center is a capacity-constrained (bottleneck) resource, operation block scheduling can be used to achieve a carefully managed schedule that maximizes the throughput without exceeding the capacity of the work center. Prior operations are backward-scheduled, while downstream operations are forward-scheduled. This is known as constraint-oriented finite loading.

Block Planning from Manufacturing Visual Planning

Use the Machine Operations Scheduling chart available with manufacturing visual planning and search for operations related to the relevant work center. You can color the operations by a characteristic code to facilitate the identification of operations that can be grouped into a block. (Only discrete characteristics entered on the Work Center/Characteristics tab can be used). Select the segments that represent operations suitable to include in a block and use the command to connect them.

Block Planning from Operation Block page

Start by creating a new operation block on the Operation Block page for the relevant work center. If applicable, specifiy the work center resource on which the preferred block to be executed. Use the Available Operations tab to find operations suitable to include in the block. Characteristics entered on the Work Center/Characteristics tab appear as dynamical columns here to make it easier to determine which operations to include in the block. Characteristic values are primarily fetched from the configuration of the shop order and secondarily from the characteristics connected to the inventory part.

Resource Share

For work centers where the resource is filled with multiple operations executed simultaneously, such as ovens, the resource share is used to determine how many operations can be included in a block. A block resource share reaching 1 indicates that the resource is full, and no more operations should be connected to it. For work centers where operations are executed in sequence, the resource share is normally not relevant.

Operation Block Scheduling

Operations in the operation block can be (re)scheduled to align their start and finish date/times with the desired operation block start date/time. To trigger the operation block scheduling, click the Schedule Operation Block on the Operation Block page, or enable the Schedule option on the Connect Operations to Operation Block assistant.

For a work center resource executing multiple operations simultaneously, select to schedule the operations in parallel. Then either manually enter the start date/time or select the block that should precede this one, which will set the start date/time the same as the finish date/time of the preceding block. Once executed, all operations in the block will be forward scheduled from the given start date/time.

For a work center resource executing operations one by one, select to schedule operations in sequence. The start date/time can be entered manually or by selecting the preceding operation block. Once executed, the operations in the block will be scheduled sequentially, one after the other. The order of the operation sequence within the block is based on the original operation start date/time. Enabling Schedule with new Setup Time between Operations, all block operations with the value entered in the New Setup Time field will be scheduled, except the first one.

Schedule Operation Block with MSO

Operations in the Operation block can be finitely (re)scheduled to align their start and finish date/times with the desired operation block start date/time. To trigger the finite operation block scheduling in a MSO Static Scheduling site, click Schedule operation block with MSO on the operation block page or enable the Include Operation Blocks toggle on the Finite Scheduling basic data page. Operation Block scheduling with MSO always runs in Schedule in Sequence mode. On the assistant, select the Block that should precede this current operation block from the Preceding Block, which sets the start date/time the same as the finish date/time of the preceding block. If a Succeeding Block is selected, the end date/time of this current operation block will set the start date/time of the succeeding block.

Note: This is a limited feature, and works only with 24 hours shift working work center resources. i.e., Resources following 24x7 calendar.

Operation Block Report

An operation block can be printed using the operation block report. This report includes both detailed information about each operation connected to the operation block as well as summarized information about the total material and tool requirements. The Operation Block ID is printed as a barcode that can be scanned to populate the operations on the Shop Floor Workbench page.

APB

Operation blocks are loaded to APB and are shown as a collection of objects in the tree navigator.

APB does not consider operation block parameters when scheduling operation block. When scheduling an operation block within APB, it applies generic finite scheduling rules, i.e., operations are scheduled based on their constraints, EPST, and needs dates while also adhering to other constraints. The scheduling logic does not prioritize preferred resources nor does it specifically try to keep operations together simply because they belong to the same block.

MSO

Operations blocks are considered in finite scheduling with MSO when the Include Operation Blocks toggle is enabled on the Finite scheduling basic data page. Operation blocks consideration in MSO is treated as a hard constraint in the schedule.

In a MSO Static Scheduling site, operation blocks can be schedeuled from the Schedule Operation Block with MSO assistant which is available in the Operation Block page. In the assistant Scheduling Direction and Preferred Resource parameters can be configured. In a MSO Automatic Scheduling site the Scheduling Direction and Preferred Resource parameters are available to be changed directly from the Operation Block page header.

Note: This is a limited feature, and works only with 24 hours shift working work center resources. i.e., Resources following 24x7 calendar.

Shop Floor Workbench

Operation blocks simplify shop floor reporting. By scanning the barcode for the Operation Block ID available in the Barcode ID field of the Work Instruction - Barcode Version and Operation Block reports, the operations connected to the block are automatically populated and highlighted. All operations connected to the block can then be started simultaneously using the Start Setup/Start Production. Depending on the Concurrent Operation setting on the Work Center page, either the time share or the resource share/crew size will be split between the simultaneously started operations.