Smart Manufacturing Planning Board

Smart Manufacturing Planning Board (SMPB) is the Interactive scheduling tool designed to plan and schedule with MSO.

Data loading into these pages can be predefined as Smart Manufacturing Planning Board filters.

- Activity Description for Smart Manufacturing Planning Board Filter

Two Views in SMPB

SMPB is designed as a two page solution based on different viewing perspectives.

1. Smart Manufacturing Planning Board - Resources

This page loads Resources into the Gannt chart and shows operations assigned for each resource. (i.e. Machines, People and Tool Instances). This can be used to view and adjust allocations, as well as to change the Work Center or Labor Class assignments as a standalone tool that is designed to simplify the Work of a Manufacturing Planner.

2. Smart Manufacturing Planning Board - Operations

This page loads Operations into the Gannt chart and shows order structures scheduled over the Time. (i.e. Muti-level Shop order structures, with DOP, Project and Batch Balance information). This page has DOP header, Projects, Batch Balance columns in the Gannt thus users can view and adjust allocations, plan for multi-level Shop Orders based on Order structure-related schedules,

Both of these pages will be enabled automatically for all MSO dataset enabled sites. The Scheduling status of the MSO scheduling service is shown in SMPB pages with latest schedule accepted quality and the accepted time.

In the Gantt view, the user can make Shop Order related changes, like Shop Order Operation Split, change preferred resource, selective optimization, finite operation block creation, etc.

Drag and Drop Scheduling

In SMPB, the User can adjust, drag and drop, or manually fix any operation that is required to adjust based on any business requirement.

To do this action User needs follow these steps

  1. Enable the Insert Mode to make adjustments to shop order operations.
  2. Drag and drop required operations to required time position in the time line. (Resource reassignement also will happen if user drag into another resource)
    1. All Manually made changes will be shown in Unsaved Fixed Orders list in SMPB. User can undo or unsave selected changes from this list.
    2. Upon drag ang drop action, Fixed operation will be shown in dark blue colour and affected Operations also will be shown in Light Green colour.
    3. If there is any overload situation due to manual drag and drop action Resource icon colour would be represented in Red colour. Green color icon is shown when the Resource capacity is Balanced.
  3. After performing required adjustments all manually made changes can be applied to the finite schedule upon the execution of the Finite schedule (In Manual MSO) or Save (In Automatic MSO) actions given in headers section.

 Misc. information