Create Shop Order from Shop Order Requisition
Explanation
This activity is used to create a shop order using a shop order requisition.
If the shop order requisition is created by Project Material Requirements PlanningĀ (PMRP),
the shop requisition type should be PMRP and attached with project activity
(PPSA- Program ID, Project ID, Sub-Project ID, Activity ID). When creating a
shop order from a requisition, PPSA should be copied to the shop order and the
shop order should get the pre-posting from the project.
To create shop order(s) from requisition(s). Select the relevant
requisition(s) and click Create Shop Order(s).
Prerequisites
- At least one shop order requisition with the
status Proposal Created must exist.
- If the part is serial tracked and has either Structure Effectivity or Routing Effectivity set to
Serial, serial numbers must be reserved on the shop order requisition. The serials you choose to
reserve to the shop order
requisition must be for a single structure and/or single routing alternative.
System Effects
- One or more shop orders with Shop Order Type set to
Manufacturing from
the selected shop order requisition are created.
- The ownership and owner values of the shop
order requisition will be transferred to the new shop order.
- The maximum lot
size of the part and the quantity on the shop order requisition dictate how
many shop orders are created.
- The Need Date is set the same
as the Due Date of the requisition. If Plan Manufacturing
Supply on Due Date is enabled for the part, the need date time
is set to the last working time that day according to the site
manufacturing calendar. If disabled, the need date time is set to
00:00.
- The status of the shop order requisition(s) are changed to Shop
Order Created.
- If the shop order requisition is connected to a project activity, the shop
order requisition's planned committed cost and planned committed hours are moved
to the shop order(s).
- Serial and/or lot/batch numbers reserved to the shop order
requisition(s) are transferred to the shop order(s).
- If alternate components have been used in the material requirements planningĀ netting
process, the Alternate Component Used field in the Shop Orders
page will
be indicated. This indicates that the planner should replace one or more
components to alternate components before
releasing the shop order to avoid shortage problems.