Create Shop Order Requisition Manually
Explanation
Use this activity to manually enter a shop order requisition. You can also
generate a shop order requisition from MRP, Project MRP(PMRP), Master Scheduling,
Order Proposals, Next-Level and similar planning engines.
To create a requisition manually, create a new record and enter the
required part, quantity and due date.
Prerequisites
The part being requisitioned must have a valid part revision on the start
date.
To create a requisition manually from the Production Line Management
page, a routing revision/alternate valid for the production line must have
been selected using the Routing Operation Parameters
dialog.
System Effects
- The system creates a shop order requisition.
From this requisition, you can create a shop order.
- The system automatically
generates the requisition number and suggested start date for manufacture.
The start date is calculated as the entered due date minus the part lead
time for the quantity entered. If Plan Manufacturing Supply on Due
Date is enabled for the part, the lead time is compressed with one
day since the manufacturing is planned to be finished on the same date
as the due date.
- If the requisition is created from the Production Line Management
page, the routing revision and alternate will be set based on the routing
revision/alternate selected for the production line part.