Calculate Rates for All Cost Centers

Explanation

This activity is used to calculate new rates for all cost centers at once (header level).

Prerequisites

All the accounts should be statistical and work center and labor classes should be connected with the cost center. Cost center should be defined as a code part and cost center wise account balance should be available. Allocation base should be selected for each line. The total of the allocation factors of each cost type should be equal to 100. Factors calculated status should be yes for all cost centers.

System Effects

System will be calculated new rate using the allocation factor and the actual hours based on the selected allocation base.