Create Structure from Interim Order
Explanation
This activity is used to create a DOP structure as a copy of an interim
order structure.
To create a DOP structure from an interim order structure from the
Interim Order Header page, click Create DOP.
To create a DOP structure from an interim order structure from the DOP
Header page, click Create Structure and then
Create Structure.
Prerequisites
- To perform this activity from the Interim Order Header
page, an interim order structure must have been manually created
and evaluated for the part.
- To perform this activity from the DOP Header
page, an interim order structure must have been created for the customer
order line pegged to the DOP header.
System Effects
- DOP orders are created with quantities and in a structure similar to
the interim order structure.
- The status of the DOP orders will be Unreleased unless Auto Release
has been enabled in the Settings
section on the Details tab on the DOP Header
page. In that case, the status will be Released. Releasing a DOP
order means generating a shop order or a purchase requisition for the
DOP order.
- When releasing pegged project specific DOP orders, the system will generate
project specific shop orders or purchase requisitions/purchase orders dependent
on the part type. These orders will be received into project inventory.
- A valid routing revision and buildable routing alternate will
be added for each DOP order. If no buildable or plannable routing alternate
exist for the part a DOP log is created, but the creation of the structure
will continue. If the routing is serial effective
and no serial numbers
are reserved for the DOP order a DOP log is created, but the creation of
the structure will continue.
- The due date and the start date are calculated for each DOP order in
the structure, depending on due date and start date of the parent DOP order,
lead-time and lead-time offset, where the lead-time is depending on lot
size and routing revision and alternate. These lead-times will be calculated
based on the manufacturing calendar, whereas the pegged purchases will
use the distribution calendar.