Define Execution Logic Structure Template

Explanation

This activity is used to adjust the generated execution logic structure (ELS) template to set up the correct logic sequence, for instance, by adding predecessor information.

Once the grouping elements for supporting sequencing is decided, the Complete Grouping Criteria option should be executed. When this is done, basic data for the selected grouping elements will be retrieved and the ELS template generated.

Since the predecessor relationships cannot be generated automatically you will need to manually set up the predecessor information. From the generated information in the table of the ELS Sequencing tab, by using the Define Predecessors and Successors menu option or by using the functionality in the Gantt you can set up an execution logic to be the generic sequence for performing work during a maintenance visit. Note: When changes are made in the Gantt, the data in the table will be updated automatically and vice versa. Further, it is also possible to create new records in the ELS Sequencing tab if a grouping node requires more than one predecessor definition. Once the visit has an ELS associated, all task cards and subtasks assigned to the various event codes of the maintenance visit will be assigned automatically to the relevant ELS nodes within the structure.

This activity can be performed using the Define Predecessors and Successors dialog, the ELS Sequencing tab or by drawing dependencies directly in the Gantt.

Prerequisites

System Effects