Enable Schedule of Work Types

Explanation

This activity is used to enable Budget/Forecast Types which can be used as an SOW Type, to create a Schedule of Work.

Prerequisites

Budget/Forecast Types must be entered in the Forecast Type page under IFS/Project Management.

System Effects

Enabled Forecast Types will be made available through a List of Values for creating a new Schedule of Estimate, or will be connected as a Production under Schedule of Work Defaults. Once an SOW Type is connected as a Production, it can be used to create a Schedule of Work Production.