This Activity is used to Create Schedule of Work Change Order Item lines from your existing Schedule of Work Items.
When SOW Change Order Required is enabled, Schedule of Work Change Order need to be created to update your Schedule of Work item lines once Schedule of Work is in Approved or Workstarted status.
When Change Order is going to create with existing Sales Contract Change Order, then Change Order Number need to be selected to create your SOW Change Order.
When Change Order is going to create with new Sales Contract Change Order, then Destination Sales Contract, Change Order Name and Change Type of your new Sales Contract Change Order need to be specified.
When Change Order is going to create with existing Project Contract Change Order, then Change Order Number need to be selected to create your SOW Change Order.
When Change Order is going to create with new Sales Contract Change Order, then Change Order Name and Change Type of your new Project Contract Change Order need to be specified.
When SOW Change Comment Required is enabled, you have to specify Change Comment for your Schedule of Work Items.
Schedule of Work should be in Approved or Work Started status.
Change Order should be enabled in Change Control Settings.
SOW Change Type should be defined in Schedule of Work Change Types page.
Based on selected Schedule of Work Item information, Schedule of Work Change Order Items get created.
Schedule of Work Change Order not yet created get's created along with Schedule of Work Change Order Item line.