Define Dependency between Standard Tasks

Explanation

This activity is used to define dependencies between Standard Tasks within a Service. These dependencies are useful when scheduling the work for the particular service. Select the Standard Task for which you want to define dependencies click the 'Dependencies' button and the 'Standard task dependencies on Service item' assistant will open.

Enable the 'Set Dependencies' option for the tasks which you want to set dependencies.

Prerequisites

Standard Tasks must have been defined in the service.

System Effects

As a result of this activity, standard task lines will be connected to each other in a Predecessor - Successor (Parent - Child) relationship that can be used during scheduling.