Finalize Contractual Commitments
Explanation
Finalizing the contractual commitments is considered to be a manual operation. However, if Applications for
Payment is used, the retention must be handled as well.
- When the contract is completed there is usually a final retention period agreed in the contract, a period
where the customer can report any faults to be corrected. After the retention period has expired, customers must
pay the retention amount.
- Any interim retentions should also be released at this point if not already done.