Set Base for Cost/Revenue Element
Explanation
This activity is used to select the code part that will serve as the base for the cost/revenue element used in
IFS/Project Management.
- Any code part, other than code parts assigned to functions, can be selected as a base for cost/revenue
element.
- It is not possible to change the selected code part once there is a connection between the code part value
and the cost/revenue elements in the Cost/Revenue Element per Code Part
Value page.
Prerequisites
- The company must exist in IFS Financials.
- The code part cannot not be assigned to a code part function.
System Effects
As a result of this activity, cost/revenue elements can be connected to code part values of the selected code
part in the Cost/Revenue Element per Code Part Value page.