Information sources are a combination of facts and dimensions which are structured
and holds information about a specific transaction table in IFS Cloud. Currently
there are 6 information sources based on IFS Maintenance. One or many of these
information sources can be used when creating an IFS Business Reporter report.
An overview of each information source which is mainly based on IFS Maintenance,
is given below:
General Description
Work Order Information Source is based on work orders. This information source
carries work orders in all statuses, i.e both active and historical work orders
as well as work requests and fault reports.
Reports/Analysis
- Follow up on the count of work orders based on different dimensions,
for instance status, maintenance organization and time period
- Execution time on work orders
- Waiting time before work actually started
- How many work orders originated as fault reports
- Comparison between actual start dates/actual finish dates versus other
dates on the work order
Access Types
- DataMart
- Online
Specific Attributes
- Work Order Count
Counter used to count work orders.
This
is always set to 1 (one).
- Elapsed Execution Time
The difference between Actual Finish
Date and Actual Start Date, expressed in hours.
The work time calendar
associated with the maintenance organization on the work order is used to
get working hours, i.e this measure counts real working hours, not calendar
time.
This can be used to calculate for instance MTTR (Mean Time To Repair).
- Elapsed Waiting Time
The difference between Actual Start Date
and Date Created on the work order, expressed in hours.
The work time
calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.'
This can be used to calculate for instance MWT (Mean
Waiting Time).
- Originated From Fault
This is set to 1 (one) if the work order
was registered as a Fault Report or Work Request, otherwise it is set to
0 (zero).
This can be used to compare the total number of work orders
with those that are faults to get a fault ratio.
- Late Actual vs. Late Start
This is set to 1 (one) if the Actual
Start Date was later than the Late Start Date, otherwise it is set to 0
(zero).
If not both dates are available no calculation will be made.
This is measuring if the work order was started later than it had to be
to be finished on time (based on planned execution time).
- Late Actual vs. Latest Finish
This is set to 1 (one) if the
Actual Finish Date was later than the Latest Finish Date, otherwise it is
set to 0 (zero).
If not both dates are available no calculation will
be made.
This is measuring if the work order was finished later than
when requested by the customer or orderer of the work.
- Late Actual vs. Planned Start
This is set to 1 (one) if the
Actual Start Date was later than the Planned Start Date, otherwise it is
set to 0 (zero).
If not both dates are available no calculation will
be made.
This is measuring if the work order was started later than when
it was planned or scheduled to start, i.e measuring how well the organization
is doing in the planning/scheduling process.
- Late Actual vs. Planned Finish
This is set to 1 (one) if the
Actual Finish Date was later than the Planned Finish Date, otherwise it
is set to 0 (zero).
If not both dates are available no calculation will
be made.
This is measuring if the work order was finished later than
it was planned or scheduled to finish, i.e measuring how well the organization
is doing in the planning/scheduling process.
- Late Actual vs. Earliest Start
This is set to 1 (one) if the
Actual Start Date was later than the Earliest Start Date, otherwise it is
set to 0 (zero).
If not both dates are available no calculation will
be made.
This is measuring if the work order was started later than what
the customer or orderer of the work wanted.
- Late Actual vs. Fixed Start
This is set to 1 (one) if the
Actual Start Date was later than the Fixed Start Date, otherwise it is set
to 0 (zero).
If not both dates are available no calculation will be made.
This is measuring if the work order was started later than for instance
an agreed appointment.
- Deviation Late Actual vs. Planned Start
The difference between
Actual Start Date and Planned Start Date, expressed in hours. It will only
be calculated when Actual Start Date is later than Planned Start Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was started
late if it was started late, and can be used to calculate average deviation
when used together with the corresponding count measure.
- Deviation Late Actual vs. Planned Finish
The difference between
Actual Finish Date and Planned Finish Date, expressed in hours. It will
only be calculated when Actual Finish Date is later than Planned Finish
Date.
If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization on the
work order is used to get working hours, i.e this measure counts real working
hours, not calendar time.
This is measuring how much the work order was
finished late compared to the plan if it was finished late, and can be used
to calculate average deviation when used together with the corresponding
count measure.
- Deviation Late Actual vs. Late Start
The difference between
Actual Start Date and Late Start Date, expressed in hours. It will only
be calculated when Actual Start Date is later than Late Start Date.
If
not both dates are available no calculation will be made.
The work time
calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was started
late compared to when it had to be started if it was startéd late, and can
be used to calculate average deviation when used together with the corresponding
count measure.
- Deviation Late Completed vs. Planned Completed
The
difference between Actual Finish Date and Planned Finish Date, expressed
in minutes. It will only be calculated when Actual Finish Date is later
than Planned Finish Date.
If not both dates are available no calculation
will be made.
The work time calendar associated with the maintenance
organization on the work order is used to get working hours, i.e this measure
counts real working hours, not calendar time.
This is measuring how much
the work order was finished late compared to the plan if it was finished
late, and can be used to calculate average deviation when used together
with the corresponding count measure.
- Deviation Late Actual vs. Latest Finish
The difference between
Actual Finish Date and Latest Finish Date, expressed in hours. It will only
be calculated when Actual Finish Date is later than Latest Finish Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was finished
late compared to when it was wanted to be finished, if it was finished late,
and can be used to calculate average deviation when used together with the
corresponding count measure.
- Deviation Late Actual vs. Earliest Start
The difference between
Actual Start Date and Earliest Start Date, expressed in hours. It will only
be calculated when Actual Start Date is later than Earliest Start Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was started
late compared to when it was wanted to be start, if it was started late,
and can be used to calculate average deviation when used together with the
corresponding count measure.
- Deviation Late Actual vs. Fixed Start
The difference between
Actual Start Date and Fixed Start Date, expressed in hours. It will only
be calculated when Actual Start Date is later than Fixed Start Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was started
late compared to when it had to be started for instance based on an appointment,
if it was started late, and can be used to calculate average deviation when
used together with the corresponding count measure.
- Early Actual vs. Late Start
This is set to 1 (one) if the
Actual Start Date was earlier than the Late Start Date, otherwise it is
set to 0 (zero).
If not both dates are available no calculation will
be made.
This is measuring if the work order was started earlier than
it had to be finished on time (based on planned execution time).
- Early Actual vs. Latest Finish
This is
set to 1 (one) if the Actual Finish Date was earlier than the Latest Finish
Date, otherwise it is set to 0 (zero).
If not both dates are available
no calculation will be made.
This is measuring if the work order was
finished earlier than when requested by the customer of the work.
- Early Actual vs. Planned Start
This is set to 1 (one) if the
Actual Start Date was earlier than the Planned Start Date, otherwise it
is set to 0 (zero).
If not both dates are available no calculation will
be made.
This is measuring if the work order was started earlier than
when it was planned or scheduled to start, i.e measuring how well the organization
is doing in the planning/scheduling process.
- Early Actual vs. Planned Finish
This is set to 1 (one) if
the Actual Finish Date was earlier than the Planned Finish Date, otherwise
it is set to 0 (zero).
If not both dates are available no calculation
will be made.
This is measuring if the work order was finished earlier
than it was planned or scheduled to finish, i.e measuring how well the organization
is doing in the planning/scheduling process.
- Early Actual vs. Earliest Start
This is set to 1 (one) if
the Actual Start Date was earlier than the Earliest Start Date, otherwise
it is set to 0 (zero).
If not both dates are available no calculation
will be made.
This is measuring if the work order was started earlier
than what the customer of the work wanted.
- Early Actual vs. Fixed Start
This is set to 1 (one) if the
Actual Start Date was earlier than the Fixed Start Date, otherwise it is
set to 0 (zero).
If not both dates are available no calculation will
be made.
This is measuring if the work order was started earlier than
for instance an agreed appointment.
- Deviation Early Actual vs. Planned Start
The difference between
Actual Start Date and Planned Start Date, expressed in hours. It will only
be calculated when Actual Start Date is earlier than Planned Start Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was started
early if it was started early, and can be used to calculate average deviation
when used together with the corresponding count measure.
- Deviation Early Actual vs. Planned Finish
The difference between
Actual Finish Date and Planned Finish Date, expressed in hours. It will
only be calculated when Actual Finish Date is earlier than Planned Finish
Date.
If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization on the
work order is used to get working hours, i.e this measure counts real working
hours, not calendar time.
This is measuring how much the work order was
finished early compared to the plan if it was finished early, and can be
used to calculate average deviation when used together with the corresponding
count measure.
- Deviation Early Actual vs. Late Start
The difference between
Actual Start Date and Late Start Date, expressed in hours. It will only
be calculated when Actual Start Date is earlier than Late Start Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was started
early compared to when it had to be started if it was started early, and
can be used to calculate average deviation when used together with the corresponding
count measure.
- Deviation Early Actual vs. Latest Finish
The difference between
Actual Finish Date and Latest Finish Date, expressed in hours. It will only
be calculated when Actual Finish Date is earlier than Latest Finish Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was finished
early compared to when it was wanted to be finished, if it was finished
early, and can be used to calculate average deviation when used together
with the corresponding count measure.
- Deviation Early Actual vs. Earliest Start
The difference between
Actual Start Date and Earliest Start Date, expressed in hours. It will only
be calculated when Actual Start Date is earlier than Earliest Start Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was started
early compared to when it was wanted to be start, if it was started early,
and can be used to calculate average deviation when used together with the
corresponding count measure.
- Deviation Early Actual vs. Fixed Start
The difference between
Actual Start Date and Fixed Start Date, expressed in hours. It will only
be calculated when Actual Start Date is early than Fixed Start Date.
If not both dates are available no calculation will be made.
The work
time calendar associated with the maintenance organization on the work order
is used to get working hours, i.e this measure counts real working hours,
not calendar time.
This is measuring how much the work order was started
early compared to when it had to be started for instance based on an appointment,
if it was started early, and can be used to calculate average deviation
when used together with the corresponding count measure.
Supported Dimensions
- Company
- Customer
- Site
- Equipment Objects
- Linear Asset
- Compatible Unit
- Vim Serial
- Maintenance Organizations
- Project
- Sub Project
- Activity
- Project Program
- Work Type
- Work Type Category
- Work Order Connection Type
- Service Contract Line
- Date Created
- Planned Start Date
- Planned Finish Date
- Late Start Date
- Latest Finish Date
- Actual Start Date
- Actual Finish Date
- Event
- Discovery
- Operational Status
- Priority
- Symptom
- Supplier
- Earliest Start Date
- Item Class
- Fixed Start Date
- Item Class Function
- Item Class Fault Type
- Source Connection
- Item Class Cause
- SLA Order
- PM Group
Main Features Supporting IFS Business Reporter
- Zoom In
Not supported.
- Drill Down
Not available .- Writeback
Not
available.
- URL navigation
Not available.
General Description
Work Order Budget Information Source is based on the manually entered budget
cost and revenues on work orders.
Reports/Analysis
This Information Source should mostly be used in conjunction with cost and
revenue follow-up using Information Source Work Order Actuals.
Access Types
- DataMart
- Online
Specific Attributes
- Cost Amount Budget
The total budget cost for the
work order.
- Revenue Amount Budget
The total budget revenue for
the work order.
Supported Dimensions
- Work Order
- Equipment Objects
- Linear Asset
- Compatible Unit
- Vim Serial
- Work Task Cost Type
- Company
- Site
- Maintenance Organizations
- Work Type
- Customer
- Project
- Sub Project
- Activity
- Project Program
- Work Type Category
- Work Order Connection Type
- Discovery
- Operational Status
- Priority
- Symptom
- Supplier
- PM Group
- Latest Finish Date
- Earliest Start Date
Main Features Supporting IFS Business Reporter
- Zoom In
Not supported.
- Drill Down
Not available .- Writeback
Not
available.
- URL navigation
Not available.
General Description
Work Task Planned Information Source is based on the planning lines on Work
Tasks.
Reports/Analysis
This Information Source should mostly be used in conjunction with cost and
revenue follow-up using Information Source Work Task Actuals.
Access Types
- DataMart
- Online
Specific Attributes
- Cost Amount Planned
The cost amount for the planned
line of the work task.
- Quantity to Invoice
The quantity to invoice for
the planned line of the work task.
- Quantity Planned
The quantity for plan line of the
work task.
- Sales Price Amount
The sales price amount for the
planned line of the work task.
Supported Dimensions
- Work Order
- Actual Equipment Object
- Reported Equipment Object
- Linear Asset
- Compatible Unit
- Vim Serial
- Work Task Cost Type
- Company
- Site
- Maintenance Organizations
- Customer
- Project
- Sub Project
- Activity
- Project Program
- Work Type
- Work Type Category
- Service Contract Line
- Work Task Connection Type Actual
- Work Task Connection Type Reported
- Criticality
- Source Connection
- Cause
- Class
- Planned Start Date
- Planned Finish Date
- Late Start Date
- Latest Finish Date
- Actual Start Date
- Actual Finish Date
- Earliest Start Date
- Priority
- Event
- Discovery
- Fault Type
- Performed Action
- Operational Status
- Symptom
- Contractor
- Work Task
- Work Stage
- Supplier
Main Features Supporting IFS Business Reporter
- Zoom In
Not supported.
- Drill Down
Not available .- Writeback
Not
available.
- URL navigation
Not available.
General Description
Information Source is based on the work order that can have one or more work
tasks connected to it. Work task is an entity which executes the work initiated
through a Fault Report
or Service request.
You can use this window to update information about the faulty equipment if
it differs from the reported one. Performed maintenance activities are reported,
monitored and invoiced to customer if IFS/Service Management is used, through
the work task.
Reports/Analysis
Following are some report examples that might be created based on this Information
Source:
- Division of maintenance costs on corrective maintenance and preventive
maintenance respectively
Access Types
- DataMart
- Online
Specific Attributes
- Deviation Early Actual vs. Earliest Start
The difference between
Actual Start Date and Earliest Start Date, expressed in hours.
It will
only be calculated when Actual Start Date is earlier than Earliest Start
Date.If not both dates are available no calculation will be made.
The
work time calendar associated with the maintenance organization on the work
task is used to get working hours, i.e this measure counts real working
hours, not calendar time.
This is measuring how much the work task was
started early compared to when it was wanted to be start, if it was started
early, and can be used to calculate average deviation when used together
with the corresponding count measure.
- Deviation Early Actual vs. Fixed Start
The difference between
Actual Start Date and Fixed Start Date, expressed in hours.
It will only
be calculated when Actual Start Date is early than Fixed Start Date.If not
both dates are available no calculation will be made.
The work time calendar
associated with the maintenance organization on the work task is used to
get working hours, i.e this measure counts real working hours, not calendar
time.
This is measuring how much the work task was started early compared
to when it had to be started for instance based on an appointment, if it
was started early, and can be used to calculate average deviation when used
together with the corresponding count measure.
- Deviation Early Actual vs. Planned Finish
The difference between
Actual Finish Date and Planned Finish Date, expressed in hours.
It will
only be calculated when Actual Finish Date is earlier than Planned Finish
Date. If not both dates are available no calculation will be made.
The
work time calendar associated with the maintenance organization on the work
task is used to get working hours, i.e this measure counts real working
hours, not calendar time.
This is measuring how much the work task was
finished early compared to the plan if it was finished early, and can be
used to calculate average deviation when used together with the corresponding
count measure.
- Deviation Early Actual vs. Planned Finish
The difference between
Actual Finish Date and Planned Finish Date, expressed in hours.
It will
only be calculated when Actual Finish Date is earlier than Planned Finish
Date. If not both dates are available no calculation will be made.
The
work time calendar associated with the maintenance organization on the work
task is used to get working hours, i.e this measure counts real working
hours, not calendar time.
This is measuring how much the work task was
finished early compared to the plan if it was finished early, and can be
used to calculate average deviation when used together with the corresponding
count measure.
- Deviation Early Actual vs. Planned Start
The difference
between Actual Start Date and Planned Start Date, expressed in hours.
It will only be calculated when Actual Start Date is earlier than Planned
Start Date. If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization
on the work task is used to get working hours, i.e this measure counts real
working hours, not calendar time.
This is measuring how much the work
task was started early if it was started early, and can be used to calculate
average deviation when used together with the corresponding count measure.
- Deviation Early Actual vs. Latest Finish
The difference
between Actual Finish Date and Latest Finish Date, expressed in hours.
It will only be calculated when Actual Finish Date is earlier than Latest
Finish Date. If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization
on the work task is used to get working hours, i.e this measure counts real
working hours, not calendar time.
This is measuring how much the work
task was finished early compared to when it was wanted to be finished, if
it was finished early, and can be used to calculate average deviation when
used together with the corresponding count measure.
- Early Actual vs. Earliest Start
This is set to 1
(one) if the Actual Start Date was earlier than the Earliest Start Date,
otherwise it is set to 0 (zero).
If not both dates are available, no
calculation will be made.
This is measuring if the work task was started
earlier than what the customer of the work wanted.
- Early Actual vs. Fixed Start
This is set to 1 (one)
if the Actual Start Date was earlier than the Fixed Start Date, otherwise
it is set to 0 (zero).
If not both dates are available, no calculation
will be made.
This is measuring if the work task was started earlier
than for instance an agreed appointment.
- Early Actual vs. Planned Finish
This is set to 1
(one) if the Actual Finish Date was earlier than the Planned Finish Date,
otherwise it is set to 0 (zero).
If not both dates are available no
calculation will be made.
This is measuring if the work task was finished
earlier than it was planned or scheduled to finish, i.e measuring how well
the organization is doing in the planning/scheduling process.
- Early Actual vs. Planned Start
This is set to 1
(one) if the Actual Start Date was earlier than the Planned Start Date,
otherwise it is set to 0 (zero).
If not both dates are available no
calculation will be made.
This is measuring if the work task was started
earlier than when it was planned or scheduled to start, i.e measuring how
well the organization is doing in the planning/scheduling process.
- Early Actual vs. Latest Finish
This is set to 1
(one) if the Actual Finish Date was earlier than the Latest Finish Date,
otherwise it is set to 0 (zero).
If not both dates are available no
calculation will be made.
This is measuring if the work task was finished
earlier than when requested by the customer of the work.
- Early Actual vs. Latest Start
This is set to 1 (one)
if the Actual Start Date was earlier than the Latest Start Date, otherwise
it is set to 0 (zero).
If not both dates are available no calculation
will be made.
This is measuring if the work task was started earlier
than when requested by the customer of the work.
- Deviation Late Actual vs. Earliest Start
The difference
between Actual Start Date and Earliest Start Date, expressed in hours.
It will only be calculated when Actual Start Date is later than Earliest
Start Date. If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization
on the work task is used to get working hours, i.e this measure counts real
working hours, not calendar time.
This is measuring how much the work
task was started late compared to when it was wanted to be start, if it
was started late, and can be used to calculate average deviation when used
together with the corresponding count measure.
- Deviation Late Actual vs. Fixed Start
The difference
between Actual Start Date and Fixed Start Date, expressed in hours.
It will only be calculated when Actual Start Date is later than Fixed Start
Date. If not both dates are available no calculation will be made.
The
work time calendar associated with the maintenance organization on the Work
Task is used to get working hours, i.e this measure counts real working
hours, not calendar time.
This is measuring how much the Work Task was
started late compared to when it had to be started for instance based on
an appointment, if it was started late, and can be used to calculate average
deviation when used together with the corresponding count measure.
- Deviation Late Actual vs. Planned Finish
The difference
between Actual Finish Date and Planned Finish Date, expressed in hours.
It will only be calculated when Actual Finish Date is later than Planned
Finish Date. If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization
on the Work Task is used to get working hours, i.e this measure counts real
working hours, not calendar time.
This is measuring how much the Work
Task was finished late compared to the plan if it was finished late, and
can be used to calculate average deviation when used together with the corresponding
count measure.
- Deviation Late Actual vs. Planned Start
The difference
between Actual Start Date and Planned Start Date, expressed in hours.
It will only be calculated when Actual Start Date is later than Planned
Start Date. If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization on the
Work Task is used to get working hours, i.e this measure counts real working
hours, not calendar time.
This is measuring how much the Work Task was
started late if it was started late, and can be used to calculate average
deviation when used together with the corresponding count measure.
- Deviation Late Actual vs. Latest Finish
The difference
between Actual Finish Date and Latest Finish Date, expressed in hours.
It will only be calculated when Actual Finish Date is later than Latest
Finish Date. If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization
on the Work Task is used to get working hours, i.e this measure counts real
working hours, not calendar time.
This is measuring how much the Work
Task was finished late compared to when it was wanted to be finished, if
it was finished late, and can be used to calculate average deviation when
used together with the corresponding count measure.
- Deviation Late Actual vs. Latest Start
The difference
between Actual Finish Date and Latest Start Date, expressed in hours.
It will only be calculated when Actual Finish Date is later than Latest
Start Date. If not both dates are available no calculation will be made.
The work time calendar associated with the maintenance organization
on the work task is used to get working hours, i.e this measure counts real
working hours, not calendar time.
This is measuring how much the work
task was finished late compared to when it was wanted to be finished, if
it was finished late, and can be used to calculate average deviation when
used together with the corresponding count measure.
- Elapsed Waiting Time
The difference between Actual
Start Date and Date Created on the Work Task, expressed in hours.
The
work time calendar associated with the maintenance organization on the Work
Task is used to get working hours, i.e this measure counts real working
hours, not calendar time.
This can be used to calculate for instance
MWT (Mean Waiting Time).
- Late Actual vs. Earliest Start
This is set to 1
(one) if the Actual Start Date was later than the Earliest Start Date, otherwise
it is set to 0 (zero).
If not both dates are available no calculation
will be made.
This is measuring if the Work Task was started later than
what the customer or order of the work wanted.
- Late Actual vs. Fixed Start
This is set to 1 (one)
if the Actual Start Date was later than the Fixed Start Date, otherwise
it is set to 0 (zero).
If not both dates are available no calculation
will be made.
This is measuring if the Work Task was started later than
for instance an agreed appointment.
- Late Actual vs. Planned Finish
This is set to 1
(one) if the Actual Finish Date was later than the Planned Finish Date,
otherwise it is set to 0 (zero).
If not both dates are available no
calculation will be made.
This is measuring if the Work Task was finished
later than it was planned or scheduled to finish, i.e measuring how well
the organization is doing in the planning/scheduling process.
- Late Actual vs. Planned Start
This is set to 1 (one)
if the Actual Start Date was later than the Planned Start Date, otherwise
it is set to 0 (zero).
If not both dates are available no calculation
will be made.
This is measuring if the Work Task was started later than
when it was planned or scheduled to start, i.e measuring how well the organization
is doing in the planning/scheduling process.
- Late Actual vs. Latest Finish
This is set to 1 (one)
if the Actual Finish Date was later than the Latest Finish Date, otherwise
it is set to 0 (zero).
If not both dates are available no calculation
will be made.
This is measuring if the Work Task was finished later
than when requested by the customer or order of the work.
- Late Actual vs. Latest Start
This is set to 1 (one)
if the Actual Finish Date was later than the Latest Start Date, otherwise
it is set to 0 (zero).
If not both dates are available no calculation
will be made.
This is measuring if the work task was finished later
than when requested by the customer or order of the work.
- Task Count
Counter used to count work Tasks.
- Elapsed Execution Time
The difference between the Actual Finish
Date and Actual Start Date.
- Total Actual Cost Amount
The total actual cost amount
incurred on the work task. This is used for the calculation of Planning
Varience Index.
- Total Planned Cost Amount
The total planned cost
amount for the work task. This is used for the calculation of Planning Varience
Index.
Supported Dimensions
- Work Order
- Actual Equipment Object
- Reported Equipment Object
- Actual Object Site
- Cancel Task Cause
- Date Reported
- Source Connection
- Project Program
- Reported Object Site
- SLA Order Line
- Source Object
- Sub Project
- Company
- Site
- Maintenance Organizations
- Customer
- Project
- Activity
- Work Type
- Work Type Category
- Service Contract Line
- Work Task Connection Type Actual
- Work Task Connection Type Reported
- Cause
- Class
- Planned Start Date
- Planned Finish Date
- Late Start Date
- Latest Finish Date
- Actual Start Date
- Actual Finish Date
- Earliest Start Date
- Priority
- Event
- Discovery
- Fault Type
- Performed Action
- Operational Status
- Symptom
- Work Stage
- Supplier
- PM Group
- SLA Latest Start
- SLA Latest Finish
- Source Site
- Item Class
- Item Class Source
- Item Class Function
- Item Class Cause
- Failing component
- Operational Status
Main Features Supporting IFS Business Reporter
- Zoom In
Not supported.
- Drill Down
Not available .- Writeback
Not
available.
- URL navigation
Not available.
General Description
Work Task Actuals Cost Information Source is based on the cost for task that
has been performed on work Task. This information source carries transactions
for Expenses, External, Fixed Price, Material, Personnel, and Tool/Equipment.
Reports/Analysis
Following are some report examples that might be created based on this Information
Source:
- Division of maintenance costs on corrective maintenance and preventive
maintenance respectively
- Calculation of cost and revenues on service contracts
- Division of maintenance costs between internal maintenance organizations
and external costs per supplier
- Maintenance costs and revenues per customer
- Work Order costs and revenues per program, project, subproject and/or
project activity
Access Types
- DataMart
- Online
Specific Attributes
- Cost Amount
The quantity of the item or service on the sales
line. For instance, the number of hours a tool was utilized for the work.
- Quantity
The total cost of the transaction. This is the cost
of the item or service * reported quantity. For instance, if 2 hours is
reported for a mechanic whose per hour cost is 100 USD, the total cost on
the cost line = 200 USD.
Supported Dimensions
- Work Order
- Actual Object Site
- Cancel Task Cause
- Date Reported
- Project Program
- Reported Object Site
- Source Object
- Sub Project
- Actual Equipment Object
- Reported Equipment Object
- Work Task Cost Type
- Company
- Site
- Maintenance Organizations
- Customer
- Project
- Activity
- Work Type
- Work Type Category
- Service Contract Line
- Work Task Connection Type Actual
- Work Task Connection Type Reported
- Cause
- Class
- Planned Start Date
- Planned Finish Date
- Late Start Date
- Latest Finish Date
- Actual Start Date
- Actual Finish Date
- Earliest Start Date
- Priority
- Event
- Discovery
- Fault Type
- Performed Action
- Operational Status
- Symptom
- Work Task
- Work Stage
- Supplier
- PM Group
- SLA Latest Start
- SLA Latest Finish
- Source Site
- Item Class
- Item Class Source
- Item Class Function
- Item Class Cause
- Failing component
- Source Connection
- Company Reporting Period
Main Features Supporting IFS Business Reporter
- Zoom In
Not supported.
- Drill Down
Not available .- Writeback
Not
available.
- URL navigation
Not available.
General Description
Work Task Actuals Sales Information Source is based on the sales for task
that has been performed on work Task. This information source carries transactions
for Expenses, External, Fixed Price, Material, Personnel, and Tool/Equipment.
For instance, a sales lines will be generated when issuing material for a work
task and sales parts have been connected.
Reports/Analysis
Following are some report examples that might be created based on this Information
Source:
- Division of maintenance costs on corrective maintenance and preventive
maintenance respectively
- Calculation of cost and revenues on service contracts
- Division of maintenance costs between internal maintenance organizations
and external costs per supplier
- Maintenance costs and revenues per customer
- Work Order costs and revenues per program, project, subproject and/or
project activity
Access Types
- DataMart
- Online
Specific Attributes
- Quantity
The quantity of the item or service on the sales
line. For instance, the number of hours a tool was utilized for the work.
- Quantity To Invoice
The quantity of the item or service that
is to be invoiced.
- Sales Price
The base price of the item or service, shown in
the company currency.
- Sales Price Amount/Base
The price of the item or service,
including any discounts, and shown in the company currency.
- Sales Price Amount/Curr
The sales price of
the item or service, including any discounts, and shown in the customer's
currency. Sales Price * Qty to Invoice - discounted amount).
Supported Dimensions
- Work Order
- Actual Object Site
- Cancel Task Cause
- Date Reported
- Source Connection
- Project Program
- Reported Object Site
- Sales Part
- Source Object
- Sub Project
- Actual Equipment Object
- Reported Equipment Object
- Work Task Cost Type
- Company
- Site
- Maintenance Organizations
- Customer
- Project
- Activity
- Work Type
- Work Type Category
- Service Contract Line
- Work Task Connection Type Actual
- Work Task Connection Type Reported
- Cause
- Class
- Planned Start Date
- Planned Finish Date
- Late Start Date
- Latest Finish Date
- Actual Start Date
- Actual Finish Date
- Earliest Start Date
- Priority
- Event
- Discovery
- Fault Type
- Performed Action
- Operational Status
- Symptom
- Work Task
- Work Stage
- Supplier
- PM Group
- SLA Latest Start
- SLA Latest Finish
- Source Site
- Item Class
- Item Class Source
- Item Class Function
- Item Class Cause
- Failing component
- Operational Status
Main Features Supporting IFS Business Reporter
- Zoom In
Not supported.
- Drill Down
Not available .
- Writeback
Not available.
- URL navigation
Not available.
General Description
Work Task Accounting
Information Source is based on transactions related to work tasks. It is possible
to view combination of data from the
Work Order,
Work Task,
Work Task Transaction
and
Work Task Cost
windows.
Reports/Analysis
Following are some report examples that might be created based on this Information
Source:
- Division of maintenance costs on corrective maintenance and preventive
maintenance respectively
- Calculation of cost and revenues on service contracts
- Division of maintenance costs between internal maintenance organizations
and external costs per supplier
- Maintenance costs and revenues per customer
Access Types
- DataMart
- Online
Specific Attributes
- Quantity
The quantity related to the transaction, e.g., the
number of hours reported by a person.
- Total Cost
The total cost related to the transaction inclusive
of overheads, if any.
Supported Dimensions
- Company
- Account
- Actual Object Site
- Code B
- Code C
- Code D
- Code E
- Code F
- Code G
- Code H
- Code I
- Code J
- Date Reported
- Source Connection
- Project Program
- Reported Object Site
- Company Reporting Period
- Source Object
- Sub Project
- Posting Type
- Time Type
- Work Order
- Work Type Category
- Actual Equipment Object
- Reported Equipment Object
- Maintenance Organizations
- Organization Site
- Item Class
- Item Class Source
- Item Class Function
- Item Class Cause
- Failing component
- Priority
- Event
- Discovery
- Fault Type
- Performed Action
- Operational Status
- Symptom
- Transaction Type
- Work Task Cost Type
- Site
- Activity
- Cancel Task Cause
- Customer
- Project
- Planned Start Date
- Planned Finish Date
- Late Start Date
- Latest Finish Date
- Actual Start Date
- Actual Finish Date
- Earliest Start Date
- Work Type
- Service Contract Line
- Work Task Connection Type Actual
- Work Task Connection Type Reported
- Cause
- Class
- Work Task
- Work Stage
- Supplier
- PM Group
- SLA Latest Start
- SLA Latest Finish
- Source Site
- Operational Status
Main Features Supporting IFS Business Reporter
- Zoom In
Not supported.
- Drill Down
Not available .
- Writeback
Not available.
- URL navigation
Not available.
Following are some report examples that might be created
based on this Information Source:
The source of information for Equipment Object Downtime records eqipment downtimes.
Follow up on the downtime count to obtain information about the number of times
a specifi equipment was broken.