Enter Work Recording
Explanation
This activity is used to log work progress, which can be performed in the Work
Recording page. Work completed should not exceed the Item Quantity unless
the Over Production Allowed option is selected for your item line.
- You can specify the completed quantity via the Current
Quantity, Cumulative Quantity, or Progress
% fields.
- Backdated work recordings can be performed by manually specifying the Record
Date.
- Item Plan Start and Item Plan Finish dates will indicate the
date range when work recording is expected to complete.
- The person assigned to do the work recording can be specified as the Responsible
Person.
- If the status needs to be rolled back, it should be performed through the Schedule of Work
Production Management page.
Prerequisites
The schedule of work Item line must be in the Released or Started status.
System Effects
The reported quantity updates Unconfirmed Quantity until it confirmed, using the
Confirm Work Recording command.
Changes made on the lines are reflected in the Work Recording History page.