Execute Calculate Value at Work Recording Summary

Explanation

This activity will calculate the Cost and Revenue values, Progress percentage and the Earned Value based on your Production Schedule of Work. Once the function Calculation Value is performed, it is possible to analyze the SOW Production and work progress from four different perspectives:

The Details command in the Value Summary by CBS and Value Summary by Cost Elements pages will be giving the same visualization.

Prerequisites

System Effects

The defined cost/revenue sub project and activities are prioritized when executing the calculation based on the following order:

  1. Detail Level
  2. Item Level
  3. Default Sub Project and Default Activity values (on the Schedule of Work header)

Estimated Cost and Revenue values will ready to be reviewed in Project level, Sup Project Level or Activity Level based on your Schedule of Work.

Based on your selected Cost Element - Cost Type Mapping, you will be able to see the Total Cost distribution to each enabled Cost Type in the Schedule of Work Summary pages.