Execute Copy EAC to Project Forecast

Explanation

This activity is used to update the calculated estimates to the selected Project Forecast. This can be achieved by performing the Copy EAC to Project Forecast command in either the Schedule of Work Value Summary or Work Recording Summary pages.

Depending on your preference, Cost and/or Revenue values can be updated at the Project level, Sub Project level, or Activity level. The selection of Sub Project level or Activity level will be allowed only when Sub Project or Activity information is specified in all item lines of your Schedule of Work Estimate.

The Calculated Date of the Schedule of Work Estimate should fall within the range of the Cut Off Date of your selected Project Forecast.

When the Schedule of Work Version is updated, it is possible to copy the updated Cost and/or Revenue values to the same Project Forecast multiple times. However, when copying to an already updated Project Forecast, you will not be allowed to change the previously selected Levels.

Note that the Copy EAC to Project Forecast command will not update the Cost Progress to the Project Forecast. To update the Cost Progress, use the Update Project Forecast Progress command in the Work Record Summary page

Prerequisites

System Effects

Project Forecast Item lines will be created based on the calculated Cost/Revenue Element values.