Connect Request Tasks
Explanation
This is the process of connecting individual tasks to Request Bundle Tasks.
Prerequisites for the Request Bundle Task
- The Bundle Task's status must be below Work Done.
- The Bundle Task can have recorded Clocking’s.
- Transactions can exist within the Bundle Task.
Prerequisites for the connecting task
- The connecting task's status should be below Work Done.
- No Clocking's should be created for the connecting tasks.
- Transactions can exist within the tasks, not based on Work Assignments
System Effects
When you connect a task to a bundle task, the following effects occur:
- Connected task resource demands must be set as Not Allocatable.
- Allocations associated with the connected tasks will be cancelled.
- New transactions within the Bundle Task will distribute costs among
all connected tasks, while previous transactions will remain unchanged.
- Duration and assignments on the Bundle Task must be manually adjusted
to accommodate additional requirements.
- An Event Log will be created upon connection of tasks.
As a result of this activity, individual tasks will be connected to Request
Bundle Tasks.