Maintenance Resource Setup
Introduction
Service resources are
resources which have been defined in IFS/Enterprise/Resource/Resource
Details to be used in Service and Maintenance. The resource types
include persons, person groups, tool/equipment, tool/equipment groups, crew
and crew groups. When specific criteria are met the resources can be entered
on a resource demand line and be assigned to work assignments on a Request
Work Task.
Prerequisites
Person, Tool/Equipment and Crew
To use a resource in a work
task resource demand or work assignment the following is required in Resource
Details:
- Resource must be set as
Active.
- Resource must belong to at
least one parent resource group which is set as Use in Service.
- IFS Human Resources must
have been installed and the following must have been defined: Competency
Groups, Elements, Levels, and Certificates. Re srouce must belong
to a Specific Site. A resource belongs to a specific
site when it fulfills the below conditions.
- Resource must belong to at
least one parent resource group which has the specific site
connection in the Connections page.
- Resource must have the
specific site connection in the Connections page.
Note: In
addition to above:
- If IFS/Dynamic Scheduling Engine
is used and is to use a resource, it needs to be registered in Scheduling
Basic Data.
- If IFS/Mobile Work Order is used
and is to use a resource, it needs to be set as Mobile User in
the Company Settings tab in Resource
Details/Maintenance/Service page.
For a resource of type Person, a
site should be defined in the Site Settings tab in Resource
Details/Maintenance/Service page.
It is allowed to define multiple sites and maintenance organizations. If so,
one site should be set as the Primary site.
Person Group, Tool/Equipment Group and Crew Group
To use a resource in a work
task resource demand, the following is required in Resource Details:
- Resource group must be set as an Active.
- Resource group must be set as Use in Service.
- Resource group must be connected to a specific site in Connections page.
To allocate a resource
group in a specific site in MPB, in addition to the prerequisites for
persons group and tools/equipment group which are mentioned above, the
following is needed in the Connections page in Resource
Detail page for the Specific site connection:
- Capacity Calculation base set as Group.
- Scheduling Capacity set as Finite or Infinite.
If tool tracking is used in
tool/equipment groups, Tool Tracking needs to be set as Track
Check Out/In in the Resource Details/Maintenance/Service page
for the resource groups of type Tool/Equipment.
Availability of Resources
In general, resource
availability is taken from resource Calendar. There are general flows
of fetching calendar as below.
Availability of Person
- If
IFS/Human Resource is used, then the HR schedule of the person's
primary scheduling employment is taken to get the availability. This is
applicable only in IFS/Enterprise/Resource
Allocation and Monitoring Gantt and IFS/Dynamic Scheduling
Engine.
- If
there is no HR Schedule then the Calendar directly connected to
the person in IFS/Enterprise/Resource is taken to get the availability.
This is applicable only in IFS/Enterprise/Resource Allocation and
Monitoring Gantt and IFS/Maintenance Planning Board.
- If the
person's calendar is not available, then the Maintenance
Organizations Calendar connected to its primary scheduling
employment is taken. This is applicable only in IFS/Enterprise/Resource
Allocation and Monitoring Gantt and IFS/Maintenance Planning Board.
- If
there is no maintenance organization connected, then the person is
considered as not available.
Availability of
Tool/Equipment
- The Calendar directly
connected to the tool/equipment in IFS/Enterprise/Resource is taken to
get the availability. This is applicable only in IFS/Resource Allocation
and Monitoring Gantt and IFS/Maintenance Planning Board.
Availability of Person/Tool
Group
- The Calendar connected
to site connection in IFS/Enterprise/Resource is taken to get the
availability. This is applicable only IFS/Maintenance Planning Board.
Availability of Crew/Crew
Group
- The Calendar connected
to site connection in IFS/Enterprise/Resource and the tool/equipment in
IFS/Enterprise/Resource are taken to get the availability. This is
applicable only IFS/Resource Allocation and Monitoring Gantt.
Resource Capacity Calculations
To be able to achieve
correct results in resource allocation there is a pre-requisite to have the
capacity calculated for the resources. Generated capacity calculated for a
resource is a pre-requisite for the following allocation functionalities:
- Filter
by Availability in Allocate Resource Gantt for Work Tasks.
- Adjust
to Schedule in Allocate Resource Gantt and in Assign Work for Work Tasks.
- Visit
Handling on
Work Tasks to achieve multiple visits for a job based on the resources
calendar. This is not required if visit handling is done by IFS/Planning
and Scheduling Optimization.
The resource capacity is
calculated based on the resource schedule. If the Use HR Schedule option
is enabled on resource and employee is connected to the resource has an HR
Schedule defined in the Employee File this Schedule is used as the base for
the capacity. If the Use HR Schedule option is disabled then the Work Time
Calendar defined for the resource is the base for the calculated capacity.
The resource capacity is used in the allocation process in Service and
Maintenance to define the working and non-working time for the resources.
To calculate the resource
capacity for the resources it is needed to run the Calculate Resource
Capacity for the resource structure where the resources is connected to. In Application
Base Setup/Enterprise/Resource/Resource Details the option is there as a
command button option to Calculate Resource Capacity this
calculation can be done for a specific resource or for the full resource
structure. In the dialog opened from this option there is also an option to
setup a background job to continuously calculate the capacity for a certain
structure.