Pause SLA Commitments
Explanation
This activity is used to Pause SLA clock of SLA Commitments. This can be done from the Pause API provided. SLA
Commitments that need to be paused can be specified as follows,
- SLA sequence ID: Respective SLA will be paused.
- Request ID: All SLAs fulfilled by the respective request and underlying request scopes and request work tasks
will be paused.
- Scope ID: All SLAs fulfilled by the respective request scope and underlying request work tasks will be
paused.
- Request work Task ID: All SLAs fulfilled by the respective request work tasks will be paused.
- Commitment Type: If commitment type parameter is selected it will behave as an additional constraint of SLA
selection.
From the selection criteria specified, only the SLA commitments which are in Active status will
be Paused.
Prerequisites
- SLA commitments should be in Active Status.
System Effects
- SLA commitments will change into Paused status.
- Pause event in Event Log,
- For each SLA Commitment Paused, a Pause_SLA event will be created with Paused reason as
event text.
- In addition, if SLA Commitments are paused from request/scope/work task level, there will be a separate
Pause_SLA event on those entities.