Confirm Risk Analysis
Explanation
This activity is used to signal the completion of the analysis on the risk record and to change its status to
reflect this completion.
Prerequisites
A Risk Analysis ID must exist with Analysis in Progress status.
System Effects
- The status Analyzed is assigned to the risk analysis.
- On confirmation, the risk analysis is automatically assigned a Last Assessment Date and the Next
Assessment Date is calculated and displayed, based on the review period defined.
- The Risk Analysis Revision Number is increased by one.
- The risk analysis history record is inserted into the risk cost exposure records shown on Risk
Analysis/Exposure Per Revision tab.