Report Time On Bundle Task
Explanation
Time Report is used to follow up how many hours have been spent on a Bundle Task. When reporting time for a
resource it create records for the reported time and cost. Cost can be fetched from Employee Compensation, Resource
Group or Maintenance Organization.
Time Reporting will be controlled by BND_TASK_COST_DIST object property on Bundle Task. You can
define below values to the BND_TASK_COST_DIST object property,
-
EQUAL
- If you defined this value, it distributes reported time evenly among all connected work tasks.
-
PERCENTAGE
- If you defined this value, it distributes reported time based on planning percentages according to the
following equation.
- Percentage = (Reported hours/Plan Duration for the Bundle Task) X (Plan duration of the connected Work
Task)
-
MANUAL
- If you defined this value, you able to see all connected Work Tasks in the Report Time assistant. You can
select specific task to report time. Transactions are created only for the selected task/tasks.
Prerequisites
- Bundle Task must be released.
- BND_TASK_COST_DIST Object property should be defined.
- Resource to report time on Bundle Task has to be connected to relevant site in Resource Details page.
System Effects
As a result of this activity, Time Transactions are created against the respective Bundle Task and Work
tasks.
Note: In clock in and clock out, if it's in the manual time reporting option, it overrides
into equal time distribution option.