Follow up on Contract Change Order
Explanation
This activity can be used by a B2B Supplier (Contractor) to follow up on changes that are done on the change
order by the Contract Owner, such as agreed amount, status, and basic information. The Contractor is not allowed to
do any changes to the change order after they have submitted.
Prerequisites
- There are Contract Change Orders connected to any of the contracts shown in the Lobby.
- B2B-status has a value
System Effects
- All information that is visible to the Contractor, will be updated as soon as a change is done by the
Contract Owner.