Decommission Compatible Unit Revision
Explanation
This activity is used to decommission a compatible unit revision thereby scrap the connected asset. Perform the
activity by selecting the Compatible Unit from the Compatible Unit Navigator and changing
its Status to Decomissioned.
Prerequisites
- A compatible unit revision must exist, which is created for the purpose of decommissioning. i.e. This
compatible unit revision must have another revision of it which is in status Active.
- Work orders connected to the execution items, which were used to decommission the compatible unit must be
completed.
- The connected design object and equipment object should have the design status and operational status,
PlannedForScrap and Out of Operation respectively.
System Effects
- The status of the compatible unit will be set to status Decommissioned.
- Sub Units connected to the decommissioned compatible unit will also be decommissioned if they satisfy the
above prerequisites.