Writeback for Project Forecast Item in End User Mode
This is a guide on main things to remember when you execute a designed project forecast item information report
with fields enabled for writeback.
Perform Writeback
How to perform writeback can be found in the Perform Writeback
activity. Follow the steps in it with the appropriate project forecast item report selected.
Priority Order in Writeback
In IFS Cloud when you change a value in project forecast information the calculation for the rest of the
currencies and other fields is done automatically by the system. In IFS Business Analytics you should manually
modify all the fields you need that are enabled for writeback. Since there are many numeric fields that contain
estimated values in different currencies, a priority order has been preset when writing back values. This priority
order is given below.
Priority Order of Currency Values
For projects with a single currency:
- Base Currency
- Project Currency
For projects with Multi-Currency:
- Transaction Currency
- Base BF Currency
- Project
Priority Order of Estimated Values
- EAC
- ETC
- ETC Adjustment
Notes:
- The following formulas have been used when recalculating values for the above prioritized writeback.
ETC = Adjustment + ETC CCO + ETC Connected
EAC = ETC + Used + Committed
EAC = Adjustment + ETC CCO + ETC Connected + Used + Committed
- It is recommended that writeback is used only when the Online mode is enabled. If data mart or incremental
load is used there may be a mismatch in the expected results as the data that is used for editing may not be the
current data. Incremental load is enabled for the project forecast item information source.
Validations
You will get an error message if any of the following has not been completed.
When Modifying Values in Writeback Enabled Fields in a Report:
- A cost line should only contain estimated cost values and a revenue line should have estimated revenue
values.
- An exception line cannot be modified.
- A project cost/revenue element should be entered for each line.
When Inserting new lines in a Writeback Enabled Report:
- A project cost/revenue element should be entered for each new line that is added.
- There should be a currency code defined for each line.
- If the project ID is not entered it will be retrieved from the forecast.
- If the item type has not been entered it will be retrieved using the project cost/revenue element. The
cost/revenue element should not be a Node type.
- The default spread type should be set to Manual if the default profile is Manual.
Limitations
The following are limitations in IFS Business Analytics which will be addressed soon, until then you will need
to handle them manually.
- You should enter each Item ID manually for the new lines.
- The Fetch Dimension Details checkbox should be cleared when inserting new lines.
- A valid date should be entered for each new line that is entered.