Define Safe Access for Object
Explanation
This activity is used to set the value for safe access on a functional or serial object. Safe Access allows to
define if maintenance can be performed while equipment is in use. If safe access is set to required, maintenance
cannot be performed while equipment is in use and vice verca. If safe access is set to required, PM actions will be
scheduled around the currently scheduled operational plan.
Prerequisites
System Effects
- As a result of this activity, the system can derive a value for a task/operation on a work order/PM Action
occurrence planned on these objects is to be scheduling obstructive or not.
- If IFS/Maintenance Planning Board and IFS/Operational plans are used, scheduling obstructive
operations are not possible to schedule during the period where the object is in operation, when scheduling
inside maintenance planning board.