Connect Isolation Order to Permit
Explanation
Use this activity to connect existing isolation orders to permits. An isolation order can be connected to many
permits and a permit can have many isolation orders.
In addition, you can create a new isolation order that will be automatically connected to the permit. The new
isolation order can later be prepared in the Isolation Order page.
Prerequisites
To connect an existing isolation order:
- Isolation orders must be defined in Isolation Orders.
- The status of the isolation order should be between New and Establishment Completed. Note: If the
permit is in the Iso Change state you can only connect isolation orders which are in the Establishment Completed
status.
- The permit should not be approved. Note: If the permit is in the Iso Change state you can only connect
isolation orders which are in the Establishment Completed status.
- The maximum number of connections that can exist between a permit type and an isolation type should be
defined in Work Order and PM Basic Data/Allowed Connections Permit/Isolation.
To create and connect a new isolation order
- The permit should not be approved. Note: If the permit is in the Iso Change state you can only connect
isolation orders which are in the Establishment Completed status.
- The maximum number of connections that can exist between a permit type and an isolation type should be
defined in Work Order and PM Basic Data/Allowed Connections Permit/Isolation.
- Isolation types must be defined in Work Order and PM Basic Data.
To create and connect a new isolation order using an isolation
- The permit should not be approved. Note: If the permit is in the Iso Change state you can only connect
isolation orders which are in the Establishment Completed status.
- The maximum number of connections that can exist between a permit type and an isolation type should be
defined in Work Order and PM Basic Data/Allowed Connections Permit/Isolation.
- Isolations should be defined and approved in IFS/Equipment.
System Effects
As a result of this activity, isolation orders will be created (if applicable) and will be connected to the
permit.