Job Cost Periods
It is possible to define a Payment Interval in the Rate Agreement details in order to specify if the particular
rate for a job cost type is applicable for a weekly period or hourly.
- Payment Interval 'Hourly' - The rate specified will be calculated per hour for the total time
reported at the job cost calculation point.
- Payment Interval 'Weekly' - The rate specified will be applicable for total reported time for a
complete week. The week start day can be user specified (per company) in the Work Time Calendar Options sub menu
under Company Details window. A complete week is considered as 7 days from the start day (including the week
start day).
It is important to note that only complete weeks will be considered into the job cost calculations where time
registered for a week partially will not be calculated. Week Start Day can be defined by user in
Company Details page.