Analyze Labor Load Chart

Explanation

This activity is used to analyze the labor load in relation to the capacity. Load is represented with bars per day, or week and capacity with a line.

To populate the chart, click the magnifying glass and search either for relevant shop orders, or labor classes/time period depending on the page used. When searching for shop orders, chart will show all load for the relevant labor classes and dates.

The chart can be configured using below settings:

When grouping / coloring by load sources, the below classification is used:

Load SourceExplanation
PlannedLoad from a planned shop order.
ReleasedLoad from a released shop order.
StartedLoad from a started shop order.
ParkedLoad from a parked shop order.
DOPLoad from an unreleased DOP order.
RequisitionedLoad from a shop order requisition.
Master ScheduleLoad from a proposed master production schedule.
Production ScheduleLoad from a production schedule.
PromisedLoad from a capability check created interim order scheduled using IFS/APB.

To limit the contents of this chart based on a selection made in another chart, open the settings dialog by clicking the gearwheel icon and select to filter from any of below charts:

Prerequisites

System Effects