Receive Shop Order Manually
Explanation
This activity is used to receive the main product completed on a shop order to an inventory location. You can
receive complete shop order, or only a part of the lot size as well as split the receipt to different locations,
W/D/R numbers, handling units etc. Optionally you can also attach the received parts into handling units.
To manually receive a shop order from:
- The navigator, open the Receive Shop Order Manually assistant.
- Shop Order, click Receive and then Manual
Receive.
- Shop Order Tracked Structure and Shop Order Operations
Reporting, click Manual Receive.
- Shop Orders, select the order(s) to receive, click Receive and
then Manual Receive. If you select more than one order, the Receive Shop Order
Manually assistant will iterate over all selected orders.
- Shop Floor Workbench, select the last operation on a shop order, click
Receive and then Receive Manually.
In the assistant:
- Select Main Product from the Produced Part Type drop-down.
- If you want to automatically issue any not already issued material up to the received quantity, enable the
Backflush option.
- If you want to skip the normal material check, enable the Simplified Material Check option.
- If you want the completed quantity on open operations to be automatically reported so their completed
quantity plus bypass quantity equals the received quantity, enable the Auto Report Operations
option.
- If you want the status of the shop order to be set to Closed as a result of this receipt even if the
criteria for auto closure is not met, select the Force Shop Order Closure option.
- If you want the receipt to be executed in the background, enable the Background Job option.
- Enter the quantity to receive in the Qty to Receive field in the Inventory
Receipt / Serial Inventory Receipt list.
- You can either enter the quantity to receive in an existing row, or create a new row to receive it into a
new location. When creating a new row, select the relevant Location, W/D/R
No, Part Revision, Handling Unit ID etc.
- If the part is serial tracked, select the serial number to receive in the Serial No
field.
- If the part is lot/batch tracked, select the lot/batch number to receive in the Lot/Batch
No field.
- If the part has an input UoM group defined, you can enter the quantity to receive in the input unit other
than the inventory unit of measure by selecting an input UoM and enter an input qty to calculate the quantity
to receive. If the input UoM is using a formula select the row and click Input UoM, to use
the assistant.
- If the catch UoM is enabled for the part, enter the quantity to receive in the catch unit of measure in
the Catch Qty to Receive field.
To receive a shop order using Warehouse Data Collection page:
- Click Receive Shop Order.
- If the part to receive is lot/batch tracked, enter or scan lot/batch no and click Save.
- If the part to receive is serial tracked, enter or scan serial no and click Save.
- Enter or scan the handling unit ID and click Save.
- Enter or scan the quantity to receive and click Save.
- Enter or scan the location number and click Save.
- Note: The data to enter/scan may differ from the procedure described above as it depends on
both the configuration of the data capture process and the setup of the data.
Prerequisites
- A shop order of type Manufacturing, Remanufacturing, Prototype or Repair
that has reached at least the Released status must exist. The order cannot be an MRO shop order.
- At least one material line must exist on the shop order.
- If the part is serialized, the serial numbers to receive must have been reserved to the shop order. To
receive an existing serial number, the shop order type must be Remanufacturing.
- If the part is connected to a serial lifecycle group, the serial number to receive must not already exist for
another part in the same group, except if the Operational Status of the existing part serial is
Renamed, or automatic serial rename has been defined on the Serial Lifecycle
Group page. The below conditions must be fulfilled in order for automatic serial rename to occur:
- The shop order type is Remanufacturing.
- An automatic serial rename record must exist where the From Part is the part for which
the serial number currently exists, the To Part is the part to receive and the
Process is set to Remanufacturing Shop Order.
- The Operational Status of the existing part serial is not Renamed.
- The Current Position of the existing part serial must be either:
- Returned to Supplier.
- Contained and the Current Position Top Part must be Returned
to Supplier, Issued (to a customer order, project deliverables or without order
connection) or Unlocated (and the top parent Operational Status must not
be Scrapped).
- Issued (to the same shop order, a customer order, project deliverables or without
order connection).
- Unlocated and the Operational Status is
Disassembled.
- The serial number must not be defined as
a VIM, Equipment, Tool Equipment or
a Plant Design object.
- If the part is lot/batch tracked, the lot/batch numbers to receive must have been reserved to the shop order.
If the Order Type is Repair and Multilevel Repair is enabled,
there must not already exist an as-built structure for the lot/batch number and W/D/R number combination.
- If the part is multi-level tracked, the tracked structure must be completed for the received serial or
lot/batch number(s).
- If the order is connected to a control plan for which the Receipt Not Allowed option is enabled, the
control plan analysis needs to be confirmed and all time triggers need to be stopped.
- To use the Simplified Material Check feature, the part may not be multilevel tracked, and all consumed
material lines must have at least some quantity issued. Also, the Backflush option will be disabled.
- The Backflush feature for catch unit enabled components can be performed only if the full quantity on
the inventory location is issued.
- If the shop order is manually pegged to a demand, the demand order must be released.
- To receive a multilevel repair shop order:
- Parent parts must have been completely issued.
- All the serial tracked components must have been completely issued and other components must be at least
reserved.
- If the part is lot/batch tracked but not serial tracked, ensure that no as-built structure already exists
for the received lot/batch number, W/D/R number, and revision number combination.
System Effects
- The shop order main product part is received at the specified inventory location(s).
- If the Simplified Material Check option is enabled, the material will be received without verifying
that the required material has been issued to satisfy the received quantity. If this option is disabled, the
system will verify that enough material has been issued to satisfy the received quantity for all material lines
except those with Reserve/Issue Method set to Manual. For material line with manual reserve/issue
method system will only verify that some quantity has been issued.
- If the Backflush option is enabled, not already issued material will be automatically issued up the
the received quantity. The automatic issue will follow the shop order backflush rules. See the About Shop Order Material Issue for more detailed information.
- If the Auto Report Operations option is enabled, completed quantity will be reported on open
operations so their completed quantity plus bypass quantity equals the received quantity. Depending on the
setting of the Auto Report Labor Time with Quantity and Auto Report Machine Time with Quantity
drop-downs on the Work Center page, standard time for labor and machine may, or may not be reported
according to the quantity reported as complete. Note: No additional quantity will be reported as completed on
operations that already have a completed quantity plus bypass quantity that is equal to or greater than the
quantity reported on this operation.
- If the Force Shop Order Closure option is enabled, the status of the shop order will be set to
Closed even if the criteria for auto closure is not met. Note: If the criteria for auto closure is
met as a result of this receipt, the shop order will be closed even if this option is disabled.
- If the Background Job option is enabled, a background job executing the receipt will be posted. If
Force Shop Order Closure option is enabled, another background job will be posted to close the shop order.
Note: The shop order may be closed even if the background job for the receipt ends up in status
Error.
- If the part is setup as order based tracked with many lots per order allowed, but with multi-level tracked
disabled, a lot/batch number will be automatically generated and assigned to the receipt.
- If the shop order is pegged to a customer order line, the received parts are automatically reserved for the
customer order line.
- If the shop order is manually pegged to a demand, the parts will automatically be reserved for the
demand.
- If the shop order is pegged to a DOP order, the received parts is automatically reserved either to the DOP
temporary inventory, or to the shop order pegged to the parent DOP order.
- Inventory transaction history OOREC transaction(s) are created.
- If the received part is serial and/or lot/batch tracked with Multi-Level Tracking
option is enabled in the Part page, and the order type is
Manufacturing, Remanufacturing or Prototype, an as-built
structure is created and can be viewed from the As-Built Structure page.
- If the part is serialized, the reserved serial structure is moved to Part
Serial.
- If the received part is connected to a serial lifecycle group, and the serial number already exists for a
part for which automatic serial rename is defined, the existing part serial is renamed to the received part.
i.e.:
- The Current Position of the serial number for the existing part on the Part
Serial page is set to Unlocated and the Current Position to
Renamed.
- The rename is logged on the Part Serial Rename History page with the
Rename Reason set to Serial Lifecycle Rename.
- Document and technical class characteristics attached to the part serial of the renamed part are moved to
the part serial of the received part.
- For a multilevel repair shop order:
- The following changes take place in the old as-built structure data:
- If any component is salvaged (due to remove or replace repair action) in the repair, then those
component quantities will be marked in the old as-built structure as removed.
- If any component (that exists in the old as-built structure) is added to the new as-built structure,
then it will also be marked in the old as-built structure as removed.
- A new as-built structure is created as follows:
- If the parent part is lot/batch-tracking-enabled, then the lot batch number reserved in the shop
order is used for each of the lot/batch-tracking-enabled components.
- As-built revision is incremented by 1 for all the serial-tracked parent parts.
- Any of the structure components along with their sub assemblies are excluded if they have been
defined as Remove, Replace, Not Present, or
Salvage.
- All the components added through Add, Replace,
Install, and repair actions are included. Exception: Components added
with Add as the repair action and Exclude from As-Built structure
enabled will not be added to the new as-built structure.
- If there were structure changes defined, then the part revision is saved for parent parts as
given.
- You can view the new as-built structure created on the As-Built Structure
page.
- If the Close Code drop-down is set to Auto Close and the total quantity of
parts received is within the closure tolerance defined for the shop order, the status of the shop order is
changed to Closed.
- Project: If the shop order is pegged to a project miscellaneous demand or a project item,
the material is automatically reserved to the demand source.
- Project activity: If the shop order is connected to a project activity the parts are
received into the project inventory.
- Project delivery: If the shop order is created from the project delivery, the delivery
project is updated with the quantity received.
- Project miscellaneous demand: If the shop order is created from project miscellaneous
demand, the project miscellaneous demand record will be updated with the quantity received. If the shop order is
pegged to a project miscellaneous demand or a project item, the material will be automatically reserved to the
demand source.
- If the Pack option is enabled, the Pack step will appear in the
assistant. See Pack Shop Order Receipt for more detailed
information.
- If the shop order has a pegged direct demand shop order with a material line which requires the received
part, it will be automatically reserved to this material line up to its remaining quantity to reserve. If the
part is required as an alternate component on a pegged direct demand shop order, an automatic replacement to this
part will be performed for the material line up to its remaining quantity to reserve, and the received quantity
will be reserved to the replacement material line. If the received part is required on more than one material
line on pegged direct demand shop order(s), the logic will prioritize the material line with the earliest
required date. Note that in addition to the part number, also the configuration, ownership, and condition code of
the received part must match the material line on the pegged direct demand order.